| Goals and
Timeline... |
|
|
 |

|
Update to
Milestones - As of 02/10/2009
|
|
ACTIVITY
|
DATE
|
COMMENTS
|
|
High-Level Business Process
Documentation
|
December - February 2008
|
Completed
|
|
Lawson PM & City PM Project Meeting
|
December - February 2008
|
Completed
|
|
City Technical Staff Training (websphere)
|
May 15 - May 19, 2008
|
Completed
|
|
Project Kick-Off Meeting
|
March 3, 2008
|
Completed
|
|
Lawson Staff Will Begin Working
On-Site
|
March 3, 2008
|
Completed
|
| Hackett Workshops |
March 17 - April 10, 2008
|
Completed
|
|
Lawson Software Installation
|
March 17 - April 4, 2008
|
Completed
|
|
Lawson On-Site City Staff Training
|
April 14 - May 9, 2008
|
Completed
|
|
Lawson Business Intelligence
Installation
|
April 4, 2008 / April 21, 2008
|
Completed
|
|
City Technical Training @ Lawson
|
April 14 - April 18, 2008
|
Completed
|
|
Lawson Application Exploration
|
May 14 - May 31, 2008
|
Completed
|
|
City Lawson Security Training @
Lawson
|
July 7 - July 10, 2008
|
Completed
|
|
Design and Configuration of Core
Lawson Applications
|
June - July 2008
|
Completed
|
|
Acceptance Testing
(Core Design)
|
August - October 2008
|
Finalizing
|
|
Advanced Tools Design/Testing
(Business Intelligence)
|
October 2008 - April 2009
|
In Progress
|
|
Full Scale System/Volume Testing
|
*
|
|
|
Final System Preparation / End-User
Training
|
*
|
|
|
Go-Live
|
*
|
Two Successful Pay Cycles
|
|
Projected Project Completion -
Phase One
|
*
|
Project close out - after two pay
cycles
|
|
* To be updated following advanced Tools Design